Summary: Writ Petition filed by the appellant herein praying inter alia for issuing directions to the respondents to pay additional compensation for the entire land area, subject matter of the Notification dated 12th December, 2008, issued under Section 20(E)(1) of the Indian Railways Act , 1989, at the rate higher than 5% per month – In appeal, SC observed: Appellant would be entitled to additional compensation for the delay in making the award @ not less than 5% of the value of the award for each month’s delay- The appellant is held entitled to additional compensation for the left out portion of land at least @ 5% of the value of the award for a period spreading over 84 months.